|
Aviation & Flight InformationThe Critical Path for Extreme Project Management
by:
Shaun Hasan Ajani
The Extreme Project Manager (EPM) stays at a high level, and understands the big picture, at the same time being able to call the shots like a military commander. However, there are certain things, which can affect the general schedule, and the EPM must be aware of them at a comparatively
acute level. Particularly, I am referring to Critical Path Know-how
(CPM) and Project Evaluation Review Technique (PERT). The EPM wish use these analyses in a slightly several way to stay at a certain level.
Walk the Path
I have faint memories of hearing simply about CPM and Impertinent once
I was a kid, galore years ago. So what are such old ideas doing in the EPM topic? I could say that these are really important methods that every Project manager should know.
But then how would-be I be any different? And as a Project Manager, you probably cognize CMP and Impertinent well anyhow… Right? Well, I wish do it worth it for you. In a truly EPM fashion, we wish hit on CPM and PERT, in a casual and a slightly several way, wherever
you can use it simply enough to give you several kind of a handle in keeping an eye on scheduling.
CPM lets you see the sequence of events of all the tasks, and the time required. It besides shows the earliest finish, earliest start, latest finish, and latest start estimates, so you can see the slack in each of these tasks. You need to cognize the slack, because if you are seeing a sequence of events, then you are besides seeing the dependencies of each of these tasks.
Hence, if you are aware of the slack, then you can get a better idea of the adherence to schedule your project is enjoying. As an EPM, here is a way I found to do this simple: Once
you do the CPM, do not use sub-tasks. Try and stick to summary tasks. However, unlike the Activity Breakdown Structure (WBS), wherever
we use a similar method, you may have to use several of your sub-tasks, depending on the time to completion of that task. For example, if a sub-task takes a long time to complete, and has galore dependencies, use it in the CPM.
Look on the Bright Side
Yes, even as Project Managers are optimistic, especially EPM’s. Although, working with PERT, you have to be both, optimistic and pessimistic. Here is what I mean. Like CPM and WBS, Impertinent besides involves the breaking down of the project into tasks. You then must divide the tasks into three schedule categories, most optimistic stop estimate, and most bearish stop estimate, and most likely.
Lets say the task of putt the stealing paint on your time machine is most likely going to take three weeks. You must besides then consider what is the longest it wish take, and what is the shortest figure of time it wish take to apply that paint. For example, five weeks and two weeks, respectively.
Here is the advantage of this know-how
in EPM. You can manipulate your timelines effectively. If you feel that the innovational schedule is running a bit thin, and the overall project forecast was too optimistic, then you can give the bearish estimate a little much weight. For example, in this case, you can assign the timeline of six weeks to the paint job. Then, in the final Impertinent analysis, you wish see the results skew to a longer forecast.
Here is how an EPM can use the information from Impertinent analysis. As the project stakeholders are much high-strung simply about technical tasks running over schedule (and justly so), due to much chances of complications, a project overshooting its schedule due to a paint job wish be a lot less painful to the stakeholders. This wish allow you to give a lot less explanations, and use your time sagely to deliver the project on time. Of course, as a professional Project Manager, you cognize that if your project is actually in trouble, do not use this technique to hide from reality.
Like I mentioned, you probably cognize CPM and Impertinent well. However, if you do not, I encourage you to seek it out and use it in your projects. There are galore books and white papers written on it. If you are a traditional Project Manager, you can use these methods to tell you another important factors in your tasks as well. For example, if you notice the Impertinent estimates to be off by greater margins, then you must take a closer look at the task, as it is indicating greater risk, then a task that has a smaller spread.
Keep at a high level, and trust your team leads, by delegation the much specific analysis to them. And always remember, if you are an EPM, then use all this information to always support the ultimate goal of the client, as your most fundamental requirement.
Just simply about THE AUTHOR
Shaun H. Ajani is the author of books "Extreme Project Management". He has been promulgated in galore national and international magazines. Shaun has worked with aviation, IT, retail, HR, finance, education, and training industries, in companies like Motorola, Dollar Stores, Nation Gifts, Code Factory, Washington Mutual, Capital of idaho Cascade, and Sears. Shaun Ajani consults as a Certified Project Manager in Chicago at Spherion.
| |